page 1
page 2
page 3
page 4
page 5
page 6
page 7
page 8
page 9
page 10
page 11
page 12
page 13
page 14
page 15
page 16
page 17
page 18
page 19
page 20
page 21
page 22
page 23
page 24
page 25
page 26
page 27
page 28 page 29
page 30
page 31
page 32
page 33
page 34
page 35
page 36
page 37
page 38
page 39
page 40
page 41
page 42
page 43
page 44
page 45
page 46
page 47
page 48
page 49
page 50
page 51
page 52
page 53
page 54
page 55
page 56
page 57
page 58
page 59
page 60
page 61
page 62
page 63
page 64
page 65
page 66
page 67
page 68
page 69
page 70
page 71
page 72
page 73
page 74
page 75
page 76
page 77
page 78
page 79
page 80
page 81
page 82
page 83
page 84
page 85
page 86
page 87
page 88
page 89
page 90
page 91
page 92
page 93
page 94
page 95
page 96
page 97
page 98
page 99
page 100
page 101
page 102
page 103
page 104
page 105
page 106
page 107
page 108
page 109
page 110
page 111
page 112
page 113
page 114
page 115
page 116
page 117
page 118
page 119
page 120
page 121
page 122
page 123
page 124
page 125
page 126
page 127
page 128
page 129
page 130
page 131
page 132
page 133
page 134
page 135
page 136
page 137
page 138
page 139
page 140
page 141
page 142
page 143
page 144
page 145
page 146
page 147
page 148
page 149
page 150
page 151
page 152
page 153
page 154
page 155
page 156
page 157
page 158
page 159
page 160
page 161
page 162
page 163
page 164
page 165
page 166
page 167
page 168
page 169
page 170
page 171
page 172
page 173
page 174
page 175
page 176
page 177
page 178
page 179
page 180
page 181
page 182
page 183
page 184
page 185
< prev - next > Energy Hydro power civil_works_guidelines_for_micro_hydro (Printable PDF)
26 CIVIL WORKS GUIDELINES FOR MICRO-HYDROPOWER IN NEPAL
value, the orifice surface will be scoured. For micro-hydro, the
recommended velocity (V) through the orifice during normal
flow is 1.0-1.5 m/s. Starting with a small orifice opening for
normal flow (i.e., high velocity) will limit excess flow during
floods, since the discharge through the orifice is proportional
to the square root of the difference between the water level in
the river and the headrace canal (hr - hh). However, if the
orifice is directly at the river (without a trashrack) the velocity
should be less than 1.0 m/s to avoid drawing bedload into the
intake. The size of the orifice is calculated as follows:
Assuming a maximum velocity of 1.5 m/s through the orifice,
calculate the required area of the orifice opening using
Q = V x A.
For a rectangular opening, A = W x H
where W is the width and H is the height of the orifice. Set
H according to the river and ground conditions and calculate
W.
To ensure submerged condition, arrange the orifice opening
such that the water surface level at the headrace canal is at
or slightly higher (say up to 50 mm) than upper edge of the
orifice. Note that the design of headrace canal is covered in
Chapter 4. Hence the design of different micro-hydro
components are interdependent. Now calculate hr for the
design flow conditions. The hr is the water level that needs
to be maintained in the river during normal conditions. If
the actual level in the river is less, repeat the calculations
with larger width and smaller height of the orifice. If the
actual river level is still less provide a weir with weir crest
level at hr
Calculate the flow through the orifice for flood condition
(hr = design flood level). The excess flow (i.e., flow during
flood less the design flow) will have to be spilled back into
the river or nearby gullies in the initial reach of the
headrace. This is discussed in the next Chapter.
An example of an orifice sizing is shown in Example 3.1
3.6 Diversion weirs
3.6.1 GENERAL
A weir is required if the flow cannot be diverted towards the
side intake without raising the river water level, especially
during the low flow season. The weir may be of temporary,
semi-permanent or permanent construction. A temporary weir
is the preferred option for micro-hydro schemes. In planning
Example 3.1 Sizing of an orifice
Choose a suitable size of an orifice for a design flow of 2501/s. The normal water level in the river is 0.8 m above the bed level.
The design flood level is about 0.7 m above the normal water level. What is the discharge through the orifice during such a
flood?
Q = 0.250 m3/s
Set V = 1.2 m/s
Orifice area (A) = Q = 0.25 = 0.21 m2
V 1.2
Set
orifice
height
(H)
=
0.20
m
and
Width
of
orifice
(W)=
A
H
=
0.21
0.20
=1.05
m
Set bottom of orifice 0.2 m above the river bed level. This will minimise the bed load. Also, set the datum at the river bed level.
Set water level at headrace canal, hh = 0.5 m with respect to the datum as shown in Figure 3.6 (i.e. 100 mm above the upper
edge of orifice to ensure submerged condition). Note that later the headrace canal will have to be designed accordingly.
Q = AC 2g (hr-hh)
Assume C = 0.6 for roughly finished masonry orifice.
Q = 0.21 x 0.6 2 x 9.8 x (0.8-0.5)
= 0.31 m3/s or 3101/s
Qrequired = 2501/s: Therefore orifice size is OK.
Discharge through the orifice during flood flow:
hr - hh = 0.8 + 0.7 - 0.5 = 1.0 m
Qflood = 0.21 x 0.6 2 x 9.8 x 1.0 = 0.56 m3/s
Qflood = 560 1/s
The dimension of the orifice and the levels are shown in Figure 3.6. Note that the excess flood flow
can be discharged via a spillway at the gravel trap or another suitable location. A second option is to
install another orifice (double orifice system) downstream.